China Resources Haifeng Power Plant 3.8MW rooftop distributed photovoltaic power generation project PC general contracting project tender announcement

China Resources Haifeng Power Plant 3.8MW Roof Distributed Photovoltaic Power Generation Project
PC general contracting project
Tender Notice
Tender Notice ZBGG201612318
Entrusted by the tenderee, the tender for the 7th batch of China Resources Power Huanan Region's 2016 batch of tenders for the general contracting project of the 3.8MW rooftop distributed photovoltaic power generation project of China Resources Haifeng Power Plant was open tendered.
I. Basic situation of the project
Tenderee: China Resources Power (Haifeng) Co., Ltd.
Project Location: Haifeng
Project funding source: self-raised
Overall progress of the project: see the tender documents
Second, the tender situation and bidder qualification requirements
(I) Tender No.: S04019816GZ0005XM
(B) Title: PC General Contracting Project
(3) Tenderee: China Resources Power (Haifeng) Co., Ltd.
(IV) Bidding content and scope: China Resources Haifeng Power Plant 3.8MW rooftop distributed photovoltaic power generation project PV modules, photovoltaic module foundations and supports, current collector lines, inverters, combiner boxes, box transformers, communication systems, control and protection equipment, Transformer equipment, lightning protection and grounding equipment and materials procurement and installation, as well as the corresponding construction, commissioning and other projects. The procurement, construction, commissioning and service of this project (including completion acceptance) and the final stage of production and transfer in accordance with the standard.
(5) Qualifications and performance requirements of bidders:
1. Independent legal persons registered in the territory of the People's Republic of China (excluding Hong Kong, Macao and Taiwan).
2. The bidder does not belong to the executor.
3. The bidding PV module is certified by TUVULVDE or an equivalent third-party certification, and has a reliability test report issued by a professional testing organization with ISO Guide 25 qualification in accordance with national standards (or IEC standards).
4. The unit responsible for construction must obtain an effective safety production license.
5. Having qualifications for third-grade and above general contracting for power engineering construction.
6. From December 31, 2013 to December 31, 2016, there will be at least one EPC or PC general contracting performance for photovoltaic power plants of 10MW or above, and provide performance certification documents (scanned contracts, including project scope, signature page).
7. The project manager has a Class 1 constructor qualification certificate.
8, accept the Commonwealth bid, the consortium must meet the above qualifications, performance requirements.
(VI) Main indicators:
(VII) Delivery/Construction Date: Planned Commencement Date: February 18, 2017
Planned completion date: May 28, 2017
PV Module Arrival Date: March 28, 2017
(8) Remarks:
Note: Please refer to the bidding documents for details. The bidding documents shall prevail.
Third, the issue of tender documents
(I) Time and place of sale
December 30, 2016 - January 09, 2017

Wireless Charger Pad

We accept Personalized logo Wireless Charger Pad Service. Let our team of experts design and build your very own Wireless charger Pad.All you need to do is send us a photo or sketch, we will then send you a FREE mockup of your design for approval.We are a professional Chinese manufacturer of Wireless charger Pad , and look forward to your cooperation!

Wireless Charger

Wireless charger PadFast Wireless charger Pad

China Wireless Charger Pad,Qi Wireless Charger Pad,Fast Wireless Charger Pad,Fast Qi Wireless Charger Pad Manufacturer

Reteck Electronic Co., Ltd. , https://www.reteck.com

Posted on